States Strive to Eliminate Costly Construction Delays

LIUSHENGFILM / Shutterstock.com

Some states, recognizing the economic and environmental costs of delayed transportation projects, are starting to use financial incentives, heightened public scrutiny and “design-build” strategies to increase the likelihood that projects will come in on time and on budget.

This article was originally published at Stateline, an initiative of The Pew Charitable Trusts, and was written by Katherine Barrett and Richard Greene.

Once it’s done, the 52-mile Northern Beltline in central Alabama will allow interstate travelers to avoid Birmingham traffic. But the $5.3-billion project has been controversial since planning began in the late 1980s.

Supporters say the project is essential to the state’s economy, while opponents decry its environmental impact. But Beltline boosters and critics agree on one thing: The project is taking a long, long time.

A road like the Beltline typically would take 15-20 years to build, according to Ronnie Baldwin, the recently retired chief engineer for the Alabama Department of Transportation. But the Federal Highway Administration recently predicted it won’t be finished until 2054 — six years later than was projected two years ago, and 65 years after funds were earmarked for a project feasibility study in 1989. So far, work has begun on less than 2 miles of the highway.

Baldwin realizes he’s not likely to live to see the project completed. “I’m 63 right now,” he said. “There are a lot of things that will happen when I’m up in heaven.”

The Alabama road is an extreme example of a common problem: Transportation projects often are completed years or even decades late. The reasons range from environmental lawsuits and bureaucratic wrangling to recalcitrant property owners and combative utility companies.

Some states, recognizing the economic and environmental costs of such delays, are starting to use financial incentives, heightened public scrutiny and “design-build” strategies to increase the likelihood that projects will come in on time and on budget.

Moving Targets

Each year, the Federal Highway Administration updates Congress on transportation projects that cost more than $500 million. Most, but not all, use federal funding. There are 101 active projects on the latest list. Of the 57 projects with completion dates that were set before 2013, 25 are behind schedule by a year or more.

Generally speaking, the longer a project drags on, the bigger the price tag. More money is spent on contracting costs, machinery, staff time, rent and fuel. Inflation takes a toll, as does the need to pay for temporary repairs to existing routes.

There are costs to the local economy, when ongoing construction makes it more difficult for commuters to get to work and prevents businesses from delivering goods and services. The environmental impact is also significant: When construction makes traffic worse, it adds to air pollution. Stopping and starting burns fuel at a higher rate than driving on the open highway, boosting emissions.

A delay is “bad for the environment. It’s bad for the economy. It’s bad for jobs. It’s bad for global competitiveness. There’s nothing good about it,” said Philip Howard, founder and chairman of Common Good, a nonpartisan group focused on good government.

Moreover, with a delayed project, “you delay the benefit the project was supposed to deliver,” said Bill Reinhardt, editor of a monthly newsletter called Public Works Financing. “If the project was supposed to be delivered in 2012 and it isn’t delivered until 2022, then you delay all that economic benefit, the lifestyle benefit and the employment benefit. If you don’t deliver the public good, the public suffers.”

Holding Contractors Accountable

Some states are pursuing various strategies to avoid such pitfalls. One is simply to require that transportation officials provide regular—and public—progress reports.

The Florida Transportation Commission produces quarterly reviews of Transportation Department spending and annual progress reports on ongoing projects. The commission has been overseeing the transportation agency since the late 1980s, but advances in information technology have allowed it to sharpen its focus. In the late 1990s, Florida transportation projects took on average 34 percent longer than expected to complete. By 2015, the average delay was down to 7 percent.

Virginia also has been aggressive about tracking projects and making the progress reports public. The state began doing so in 2000, after it became clear it would cost more—much more—than was projected in 1994 ($350 million) to widen lanes and add new bridges and ramps to a heavily traveled interchange in Fairfax County, about 15 miles from Washington, D.C. The state increased the project budget to about $676 million in 2003, and it was completed on budget in 2007.

In the second quarter of 2004, 29 percent of Virginia transportation projects were on time and 70 percent were on budget. In the fourth quarter of 2015, 84 percent were on time and 89 percent were on budget.

Many states now reward or penalize contractors depending on whether they complete a project within a set number of days. California, for example, has used incentives and penalties to accelerate the completion of projects and minimize traffic delays.

“I may pay a slight premium and that’s transparent in the contract. The time component translates to a dollar amount and that determines the working days. If they go over, there’s a penalty,” said Malcolm Dougherty, the state’s transportation chief.

A.J. de Moya, vice president of the Florida-based de Moya Group, a highway and bridge design and construction firm, has worked on many state jobs that included incentives or penalties. He says they are effective — as long as they are substantial. “The bonus has to be large enough to make it worthwhile.”

John Porcari of WSP Parsons Brinckerhoff, one of the world’s largest design, engineering and construction companies, said states are using incentives more frequently, particularly in congested urban areas.

Porcari was deputy secretary of transportation during President Barack Obama’s first term and headed Maryland’s transportation agency under two governors. He said incentives are attractive to both transportation officials and contractors.

Construction creates “huge disruptions to the traveling public, and every day you can avoid that closure means less impact on people,” he said. For contractors, “if there is a significant incentive for delivering early, they’ll do all kinds of things to get that incentive payment.”

Other states are withholding any payments until the project is close to completion.

The Port Authority of New York and New Jersey will not start paying NYNJ Link Developer LLC until its $1.5 billion Goethals Bridge reconstruction project is 70 percent complete, so the firm has a clear financial interest in keeping the work on schedule. Project completion is scheduled for late 2018, and the payout to the firm will continue for the next 35 years, during which time the private company will also take care of capital maintenance.

Design-Build

Many states are beginning to contract with a single entity to handle both the design and construction of a project. “There’s an overlap and that’s one way to compress the schedule,” Porcari said, adding that many contractors like the strategy, which increases their risk but also their profits.

Some state officials like design-build because it eliminates strife between contractors. “Instead of everyone shooting at each other, they’re all sitting around a table,” said Dougherty of California.

In 2005, the Missouri Legislature approved design-build contracting for a road reconstruction project on 12 miles of Interstate 64 near St. Louis. Without a design-build approach, it was once estimated that the project could take up to 16 years and $675 million to complete, according to the state Department of Transportation.

A flexible and innovative design-build contract contributed to the success of the project, according to King Gee, a director at the American Association of State Highway and Transportation Officials.

In 2006, a contractor signed on to design and build the road in four years. Its fee was $420 million of the final $535 million cost of the project. The construction phase took three and a half years and it was completed for $11 million less than was budgeted.

X
This website uses cookies to enhance user experience and to analyze performance and traffic on our website. We also share information about your use of our site with our social media, advertising and analytics partners. Learn More / Do Not Sell My Personal Information
Accept Cookies
X
Cookie Preferences Cookie List

Do Not Sell My Personal Information

When you visit our website, we store cookies on your browser to collect information. The information collected might relate to you, your preferences or your device, and is mostly used to make the site work as you expect it to and to provide a more personalized web experience. However, you can choose not to allow certain types of cookies, which may impact your experience of the site and the services we are able to offer. Click on the different category headings to find out more and change our default settings according to your preference. You cannot opt-out of our First Party Strictly Necessary Cookies as they are deployed in order to ensure the proper functioning of our website (such as prompting the cookie banner and remembering your settings, to log into your account, to redirect you when you log out, etc.). For more information about the First and Third Party Cookies used please follow this link.

Allow All Cookies

Manage Consent Preferences

Strictly Necessary Cookies - Always Active

We do not allow you to opt-out of our certain cookies, as they are necessary to ensure the proper functioning of our website (such as prompting our cookie banner and remembering your privacy choices) and/or to monitor site performance. These cookies are not used in a way that constitutes a “sale” of your data under the CCPA. You can set your browser to block or alert you about these cookies, but some parts of the site will not work as intended if you do so. You can usually find these settings in the Options or Preferences menu of your browser. Visit www.allaboutcookies.org to learn more.

Sale of Personal Data, Targeting & Social Media Cookies

Under the California Consumer Privacy Act, you have the right to opt-out of the sale of your personal information to third parties. These cookies collect information for analytics and to personalize your experience with targeted ads. You may exercise your right to opt out of the sale of personal information by using this toggle switch. If you opt out we will not be able to offer you personalised ads and will not hand over your personal information to any third parties. Additionally, you may contact our legal department for further clarification about your rights as a California consumer by using this Exercise My Rights link

If you have enabled privacy controls on your browser (such as a plugin), we have to take that as a valid request to opt-out. Therefore we would not be able to track your activity through the web. This may affect our ability to personalize ads according to your preferences.

Targeting cookies may be set through our site by our advertising partners. They may be used by those companies to build a profile of your interests and show you relevant adverts on other sites. They do not store directly personal information, but are based on uniquely identifying your browser and internet device. If you do not allow these cookies, you will experience less targeted advertising.

Social media cookies are set by a range of social media services that we have added to the site to enable you to share our content with your friends and networks. They are capable of tracking your browser across other sites and building up a profile of your interests. This may impact the content and messages you see on other websites you visit. If you do not allow these cookies you may not be able to use or see these sharing tools.

If you want to opt out of all of our lead reports and lists, please submit a privacy request at our Do Not Sell page.

Save Settings
Cookie Preferences Cookie List

Cookie List

A cookie is a small piece of data (text file) that a website – when visited by a user – asks your browser to store on your device in order to remember information about you, such as your language preference or login information. Those cookies are set by us and called first-party cookies. We also use third-party cookies – which are cookies from a domain different than the domain of the website you are visiting – for our advertising and marketing efforts. More specifically, we use cookies and other tracking technologies for the following purposes:

Strictly Necessary Cookies

We do not allow you to opt-out of our certain cookies, as they are necessary to ensure the proper functioning of our website (such as prompting our cookie banner and remembering your privacy choices) and/or to monitor site performance. These cookies are not used in a way that constitutes a “sale” of your data under the CCPA. You can set your browser to block or alert you about these cookies, but some parts of the site will not work as intended if you do so. You can usually find these settings in the Options or Preferences menu of your browser. Visit www.allaboutcookies.org to learn more.

Functional Cookies

We do not allow you to opt-out of our certain cookies, as they are necessary to ensure the proper functioning of our website (such as prompting our cookie banner and remembering your privacy choices) and/or to monitor site performance. These cookies are not used in a way that constitutes a “sale” of your data under the CCPA. You can set your browser to block or alert you about these cookies, but some parts of the site will not work as intended if you do so. You can usually find these settings in the Options or Preferences menu of your browser. Visit www.allaboutcookies.org to learn more.

Performance Cookies

We do not allow you to opt-out of our certain cookies, as they are necessary to ensure the proper functioning of our website (such as prompting our cookie banner and remembering your privacy choices) and/or to monitor site performance. These cookies are not used in a way that constitutes a “sale” of your data under the CCPA. You can set your browser to block or alert you about these cookies, but some parts of the site will not work as intended if you do so. You can usually find these settings in the Options or Preferences menu of your browser. Visit www.allaboutcookies.org to learn more.

Sale of Personal Data

We also use cookies to personalize your experience on our websites, including by determining the most relevant content and advertisements to show you, and to monitor site traffic and performance, so that we may improve our websites and your experience. You may opt out of our use of such cookies (and the associated “sale” of your Personal Information) by using this toggle switch. You will still see some advertising, regardless of your selection. Because we do not track you across different devices, browsers and GEMG properties, your selection will take effect only on this browser, this device and this website.

Social Media Cookies

We also use cookies to personalize your experience on our websites, including by determining the most relevant content and advertisements to show you, and to monitor site traffic and performance, so that we may improve our websites and your experience. You may opt out of our use of such cookies (and the associated “sale” of your Personal Information) by using this toggle switch. You will still see some advertising, regardless of your selection. Because we do not track you across different devices, browsers and GEMG properties, your selection will take effect only on this browser, this device and this website.

Targeting Cookies

We also use cookies to personalize your experience on our websites, including by determining the most relevant content and advertisements to show you, and to monitor site traffic and performance, so that we may improve our websites and your experience. You may opt out of our use of such cookies (and the associated “sale” of your Personal Information) by using this toggle switch. You will still see some advertising, regardless of your selection. Because we do not track you across different devices, browsers and GEMG properties, your selection will take effect only on this browser, this device and this website.