New York’s Other Costly and Long-Delayed Transportation Megaproject

Work on the East Side Access project in New York City continues deep below Grand Central Terminal.

Work on the East Side Access project in New York City continues deep below Grand Central Terminal. Patrick Cashin / MTA

 

Connecting state and local government leaders

Huzzah! The first phase of the expensive Second Avenue subway is open for business after a tortured 100-year history. But don’t overlook the even-more-expensive and delayed East Side Access project.

New York’s Metropolitan Transportation Authority, the state agency that operates New York City’s subway system, plus the Long Island and Metro-North commuter railroads, has checked a major megaproject off its long-term capital construction list: the first phase of the long-awaited Second Avenue subway line in Manhattan, which Gov. Andrew Cuomo opened for business after a festive New Year’s Eve ribbon-cutting event.

After first being proposed nearly a century ago and partially built before New York City’s 1970s fiscal crisis scuttled additional construction, a new iteration of the Second Avenue subway project got underway in 2007.

The first phase, a three-station extension of the Q line to 96th Street on the Upper East Side, was originally scheduled to open in 2013.

But construction and other delays prompted the MTA to move the anticipated opening of the now-$4.4 billion subway line to 2016.

The 86th Street Station on the Second Avenue subway line. (via Patrick Cashin / MTA)

As time was running out to meet the end-of-the-year deadline, Cuomo took a “personal, hands-on approach” to ensure the MTA and its contractors were able to finish the job, which isn’t quite done yet. (Full 24-hour subway service along the Second Avenue extension won’t be ready until Jan. 9.)

The glitzy New Year’s Eve ribbon-cutting ceremony follows the long-delayed opening of the $2.4 billion extension of the No. 7 subway line on Manhattan’s West Side in 2015 and the completion of $1.4 billion in improvements to the Fulton Street station complex in Lower Manhattan in 2014.  

While New Yorkers are rightfully celebrating the completion of the new Second Avenue subway line, they shouldn’t forget about the other long-delayed MTA megaproject that’s been slowly taking shape beneath the streets of Manhattan: East Side Access.

That MTA megaproject, which has been plagued by years of delays and escalating costs—the current price tag is $10.2 billion—will, eventually, allow Long Island Rail Road commuter trains, which currently operate out of Penn Station in Manhattan, to serve a new eight-track station deep under Grand Central Terminal via new tunneled connections to LIRR’s Main Line in Queens.

The East Side Access project (via MTA)

Like the costly Second Avenue subway, which one analysis considers to be the most expensive in the world on a per-kilometer basis, the East Side Access project has given plenty of agency officials heartburn over its years of planning difficulties, escalating costs and ongoing construction delays.

East Side Access is now at least $6.5 billion more than originally budgeted and will now likely end up opening in 2022 or 2023, roughly 13 years after its initial target completion date.

The current obstacles involve construction coordination issues with Amtrak, which controls the Harold Interlocking in Queens, a busy track chokepoint that funnels Amtrak and Long Island Rail Road service through the massive Sunnyside Yards and in and out of tunnels serving Penn Station in Manhattan.

While infrastructure wonks are rightfully concerned about the high costs of the Second Avenue subway—and should continue to press Cuomo and the MTA to better manage costs when work starts on the second phase to 125th Street in Harlem—the ongoing troubles of East Side Access should not be overlooked.

Deep under Grand Central, a new rail terminal takes shape. (via Patrick Cashin / MTA)

Back in November 2015, Benjamin Kabak of Second Avenue Sagas, the authoritative New York City transit blog, got a chance to check on in progress of the massive station cavern taking shape deep under Grand Central Terminal, and pondered many of the same questions that are again being asked with the opening of the new subway line that essentially boils down to this: Why does it cost so much more to build new infrastructure in America’s largest city compared to peer cities around the world?

Kabak wrote at the time:

It’s hard when you’re underground to look past the grandiose nature of the work. The concourses and platforms will stretch to 50th St., and the space is enormous. Plus, as the MTA has completed 60% of the work and is set to issue contracts by the end of January to cover up to 80%, there is no going back. The agency would have to pay the feds nearly as much in refunds as it would cost to simply finish this seemingly never-ending project. And yet, it’s throwing good money after bad.

Maybe in ten years we’ll look back on the East Side Access project and its Penn Station Access partner and wonder how we lived without the ability to send the LIRR to the East Side and Metro-North to the west. But today, it’s hard to see this as the MTA’s answer to London, Shanghai or Paris, and it’s much, much easier to see this as the MTA’s answer to a lack of inter-agency cooperation, costs run amok and planning in bad need in reform. This is a project that New York City ultimately needs but not at this cost.

That last line, emphasis mine, is important and could be repeated when looking at some other infrastructure megaprojects in New York, most notably the Port Authority of New York and New Jersey’s $4 billion World Trade Center “Oculus” that opened last year as a new gateway to the PATH rail system, which connects Manhattan with New Jersey.

The Oculus at the PATH World Trade Center terminus in Lower Manhattan. (Shutterstock)

It’s certainly a stunning piece of architecture, but does nothing to expand the capacity of rail service under the Hudson River, something that New York and New Jersey desperately need. Could the $4 billion that was spent on what’s essentially trophy architecture been better utilized for other transportation needs?  

Similarly, will the $10.2 billion being spent on East Side Access be worth it?

Michael Horodniceanu, the president of MTA Capital Construction, has said that it would require “a dissertation” to explain why New York megaprojects like East Side Access cost so much, as Kabak noted in 2015.

Those costly complexities are tough challenges for a governor with major infrastructure ambitions.

New York Gov. Andrew Cuomo (via Patrick Cashin / MTA

Cuomo seems to relish the role of being New York’s biggest builder since Robert Moses and has grand plans for a new Penn Station and a rail line to completely rebuilt LaGuardia Airport and is busy building a new Tappan Zee Bridge.

But if the governor wants to “welcome a new era in New York where there is no challenge too great, no project too grand, and all is possible once again," as he announced with the Second Avenue subway’s opening, he’s going to have to figure out a way to pay for it all. And that may prove to be a far more difficult task than digging tunnels, pouring concrete and building new architecturally stunning stations.

X
This website uses cookies to enhance user experience and to analyze performance and traffic on our website. We also share information about your use of our site with our social media, advertising and analytics partners. Learn More / Do Not Sell My Personal Information
Accept Cookies
X
Cookie Preferences Cookie List

Do Not Sell My Personal Information

When you visit our website, we store cookies on your browser to collect information. The information collected might relate to you, your preferences or your device, and is mostly used to make the site work as you expect it to and to provide a more personalized web experience. However, you can choose not to allow certain types of cookies, which may impact your experience of the site and the services we are able to offer. Click on the different category headings to find out more and change our default settings according to your preference. You cannot opt-out of our First Party Strictly Necessary Cookies as they are deployed in order to ensure the proper functioning of our website (such as prompting the cookie banner and remembering your settings, to log into your account, to redirect you when you log out, etc.). For more information about the First and Third Party Cookies used please follow this link.

Allow All Cookies

Manage Consent Preferences

Strictly Necessary Cookies - Always Active

We do not allow you to opt-out of our certain cookies, as they are necessary to ensure the proper functioning of our website (such as prompting our cookie banner and remembering your privacy choices) and/or to monitor site performance. These cookies are not used in a way that constitutes a “sale” of your data under the CCPA. You can set your browser to block or alert you about these cookies, but some parts of the site will not work as intended if you do so. You can usually find these settings in the Options or Preferences menu of your browser. Visit www.allaboutcookies.org to learn more.

Sale of Personal Data, Targeting & Social Media Cookies

Under the California Consumer Privacy Act, you have the right to opt-out of the sale of your personal information to third parties. These cookies collect information for analytics and to personalize your experience with targeted ads. You may exercise your right to opt out of the sale of personal information by using this toggle switch. If you opt out we will not be able to offer you personalised ads and will not hand over your personal information to any third parties. Additionally, you may contact our legal department for further clarification about your rights as a California consumer by using this Exercise My Rights link

If you have enabled privacy controls on your browser (such as a plugin), we have to take that as a valid request to opt-out. Therefore we would not be able to track your activity through the web. This may affect our ability to personalize ads according to your preferences.

Targeting cookies may be set through our site by our advertising partners. They may be used by those companies to build a profile of your interests and show you relevant adverts on other sites. They do not store directly personal information, but are based on uniquely identifying your browser and internet device. If you do not allow these cookies, you will experience less targeted advertising.

Social media cookies are set by a range of social media services that we have added to the site to enable you to share our content with your friends and networks. They are capable of tracking your browser across other sites and building up a profile of your interests. This may impact the content and messages you see on other websites you visit. If you do not allow these cookies you may not be able to use or see these sharing tools.

If you want to opt out of all of our lead reports and lists, please submit a privacy request at our Do Not Sell page.

Save Settings
Cookie Preferences Cookie List

Cookie List

A cookie is a small piece of data (text file) that a website – when visited by a user – asks your browser to store on your device in order to remember information about you, such as your language preference or login information. Those cookies are set by us and called first-party cookies. We also use third-party cookies – which are cookies from a domain different than the domain of the website you are visiting – for our advertising and marketing efforts. More specifically, we use cookies and other tracking technologies for the following purposes:

Strictly Necessary Cookies

We do not allow you to opt-out of our certain cookies, as they are necessary to ensure the proper functioning of our website (such as prompting our cookie banner and remembering your privacy choices) and/or to monitor site performance. These cookies are not used in a way that constitutes a “sale” of your data under the CCPA. You can set your browser to block or alert you about these cookies, but some parts of the site will not work as intended if you do so. You can usually find these settings in the Options or Preferences menu of your browser. Visit www.allaboutcookies.org to learn more.

Functional Cookies

We do not allow you to opt-out of our certain cookies, as they are necessary to ensure the proper functioning of our website (such as prompting our cookie banner and remembering your privacy choices) and/or to monitor site performance. These cookies are not used in a way that constitutes a “sale” of your data under the CCPA. You can set your browser to block or alert you about these cookies, but some parts of the site will not work as intended if you do so. You can usually find these settings in the Options or Preferences menu of your browser. Visit www.allaboutcookies.org to learn more.

Performance Cookies

We do not allow you to opt-out of our certain cookies, as they are necessary to ensure the proper functioning of our website (such as prompting our cookie banner and remembering your privacy choices) and/or to monitor site performance. These cookies are not used in a way that constitutes a “sale” of your data under the CCPA. You can set your browser to block or alert you about these cookies, but some parts of the site will not work as intended if you do so. You can usually find these settings in the Options or Preferences menu of your browser. Visit www.allaboutcookies.org to learn more.

Sale of Personal Data

We also use cookies to personalize your experience on our websites, including by determining the most relevant content and advertisements to show you, and to monitor site traffic and performance, so that we may improve our websites and your experience. You may opt out of our use of such cookies (and the associated “sale” of your Personal Information) by using this toggle switch. You will still see some advertising, regardless of your selection. Because we do not track you across different devices, browsers and GEMG properties, your selection will take effect only on this browser, this device and this website.

Social Media Cookies

We also use cookies to personalize your experience on our websites, including by determining the most relevant content and advertisements to show you, and to monitor site traffic and performance, so that we may improve our websites and your experience. You may opt out of our use of such cookies (and the associated “sale” of your Personal Information) by using this toggle switch. You will still see some advertising, regardless of your selection. Because we do not track you across different devices, browsers and GEMG properties, your selection will take effect only on this browser, this device and this website.

Targeting Cookies

We also use cookies to personalize your experience on our websites, including by determining the most relevant content and advertisements to show you, and to monitor site traffic and performance, so that we may improve our websites and your experience. You may opt out of our use of such cookies (and the associated “sale” of your Personal Information) by using this toggle switch. You will still see some advertising, regardless of your selection. Because we do not track you across different devices, browsers and GEMG properties, your selection will take effect only on this browser, this device and this website.